IT

Cadriano

Two industrial buildings on a disused site
Granarolo dell’Emilia, Bologna, 2025

Scroll
The building seen from the corner: the office front with the entrance portal, and the side with the loading doors
The office front and the side of the building, project render
The project

Two buildings,
ten production units

On a site of about 12,000 m², where a foundry operated until 2008, two identical buildings divided into five units each.

Each unit has a double-height warehouse on the ground floor and offices on two levels facing the street. The structure is precast reinforced concrete; the cladding panels are finished with a mix of dark marble and glass fragments that makes the facade sparkle as the light changes. Ribbon windows run around the building, and sawtooth roof lights bring daylight into the warehouses.

12,000 m²Site area
10Production units
7,078 m²Usable floor area
Coordination

One project,
ten series of documents

For each building the building permit application gathers 78 documents, divided into ten series. Each series has its own prefix and corresponds to a professional appointment: structures, building services, geology and acoustics are signed by different consultants. As architectural designer I also coordinated the specialist consultants, so that all ten series described the same building. Tap a prefix to see its documents.

Design

A Architectural

28 documents

  1. Technical design statement
  2. Site context
  3. Survey and lawful status
  4. Photographic report
  5. Site plan, clearances
  6. Planning standards: overview
  7. Planning standards: private green space
  8. Planning standards: private parking
  9. Gross floor area plan
  10. Access and internal circulation
  11. Landscape plan
  12. Dimensioned plans: ground floor
  13. Dimensioned plans: first floor
  14. Dimensioned plans: roof
  15. Layout plans: ground floor
  16. Layout plans: first floor
  17. Daylight and ventilation check
  18. Elevations and sections
  19. Roof fall-protection documentation (IPRIPI)
  20. Public parking: before the works
  21. Public parking: after the works
  22. Accessibility: report
  23. Accessibility: ground floor
  24. Accessibility: first floor
  25. Permeability: original condition
  26. Permeability: after demolition
  27. Permeability: proposed
  28. Overlay of demolition and new works
The site

From a disused foundry
to a production estate

Site plan: the foundry, the site after demolition, the two buildings with planted beds and permeable paving
  • Foundry
  • Impermeable
  • Recycled aggregate
  • Buildings
  • Grassed beds
  • Semi-permeable
Until 2008

The foundry

A foundry operated on the site: its sheds covered more than half of the plot, and the yards around them sealed the rest. The rain could not find a single metre of soil.

  • 6,400 m²covered by the foundry sheds
  • 100%impermeable surface
2007-2023

Remediation

Once the buildings were demolished, the old paving was lifted, crushed and screened on site: the certified aggregate forms the new yard. The scrap iron that came out of the sub-base was sent for recycling.

  • 5,600 m³aggregate recycled on site
  • 22 tiron recovered
2025

The project

Two twin buildings, divided into ten units. Around them, grassed beds with hedges and trees, and semi-permeable paving: more than 10% of the site lets water soak in again.

  • 1,056 m²planted beds
  • 1,136 m²semi-permeable paving
How the project took shape

One site, two permits,
ten units

The site was first divided into two halves, one for each building permit, then into ten plots, one per unit. Each plot has its own plot area, parking and green space, and a unilateral undertaking sets the development rights of each one. The buildings sit on top: four standard units just over 12 metres wide, with a double-height warehouse and offices on two levels, and a 36-metre end unit. Tap a plot to see its figures.

ABCDEFGHIL

Building A

A Standard unit

Usable floor area
498 m²
Plot area
1,236 m²
Allocated parking
169 m²
Private green space
104 m²
The standards

More green space and more parking
than the plan requires

The planning standards check drawings, added up for the two buildings. The usable floor area takes up almost all of the permitted ratio; green space and allocated parking go well beyond the minimum. The 1,790 m² of public parking are paid for in lieu.

Day and night

The same facade,
two lights

The office front

The street elevation: two floors of offices with ribbon windows shaded by brise-soleil, and the full-height entrance portal in the middle. At night the facade stays dark and only the entrance and the blades of light on the wall are lit.

Front and side

From the corner the whole volume can be read: the office block and, along the side, the long wall of the building with the loading doors and canopies.

The site

The two buildings side by side, with their sawtooth roofs, the parking along the boundary and the tree-lined green strip that closes the site.

The office front, by day The office front, at night
The front and the side, by day The front and the side, at night
Aerial view of the site with the two buildings, by day Aerial view of the site with the two buildings, at night
Elevations and sections

The same building,
from every side

The office front

The elevation facing the main road: two ribbon windows with brise-soleil and, in the middle, the entrance portal of the end unit.

The side of the units

The long front: for each unit a sectional door under the canopy with its own sign, and the ribbon windows of the first-floor offices.

The opposite front

The other long side, with the warehouse openings and the same continuous band of windows.

The end elevation

The short side opposite the offices: four ribbon windows high up, above the double height of the warehouses.

Long section

Through all the units: the double-height warehouses, the office mezzanines and, at the far end, the end unit.

Section through the sawtooth roof

The sawtooth roof brings daylight into the warehouses; above the offices the roof is flat.

Section through the offices

The office block on two levels, with the stair and the toilets, next to the warehouse.

The office front of the building The side of the units of the building The opposite front of the building The end elevation of the building Long section of the building Section through the sawtooth roof of the building Section through the offices of the building
The layout

How the units
are used

The warehouses

On the ground floor the four standard units have a double-height warehouse, with racking and toilets towards the street; the end unit has a large open space and, at the back, offices around the stair.

The offices

On the first floor, the offices of each unit, facing the ribbon windows, and those of the end unit around the stair; below, the void of the warehouses.

Layout plan of building B, ground floor Layout plan of building B, first floor

Granarolo dell’Emilia, Cadriano

Bologna

Building permit, two applications

Two production buildings
on a disused site

Client

Private

Role

Architectural designer

Coordinator of the specialist consultants

Year

2025

10

Sheet title

Complete set, 78 documents

Ten series, for each building